Western gun position update

We are making good progress with re instating the missing concrete and gully stones. We now have 16 gully stones set in place and two sections of concrete in place. A wooden mould box was made with a sheet metal insert in the bottom to give the curved shape, having copied dimensions from an original on site. Three pieces of rebar are inserted in the middle of the concrete whilst pouring it into the mould. Every 48 hours the gully stone can be taken out of the mould and set aside to dry. The complete run on this side is 68ft and then there are some damaged and missing ones on the other side of the road to tackle.