February 2024

Ground works have continued through out the winter, with the latest being as follows…. It was decide that we did not have time or permission to extend the eastern six inch gun position so it has been recorded, covered to protect the stencilling etc. and filled in to be fully excavated at a future date. The western road pictured has had the spoil that was dug out from the 9 inch gun position removed, the area where there is missing concrete cleaned up and a few more concrete gullies have been exposed. We are now waiting for the outcome of our Scheduled Monument Consent which is to re instate the missing concrete, create new concrete gullies and set back in place (as per 1891 drawing we have) and to repair damaged ones that have been exposed.